Major works to resurface a stretch of the A14 has been completed after 16 months.
The road near Stowmarket, between Haughley and Tothill from junction 47a to junction 49, is fully open after works first started on Monday, February 20, 2023.
After 494 days, motorists have driven on the new carriageways this morning as any existing contraflows have been removed.
The works have finished ahead of its revised completion as it was initially expected to finish in August, which was then brought forward to July.
The project aimed to create a smoother and safer road surface for road users using the A14.