Gallows Corner Reopening Faces Fresh Delay as Utility Issues Persist
- Safer Highways
- 2 hours ago
- 2 min read

The long-awaited full reopening of Gallows Corner has been pushed back once again, with Transport for London (TfL) confirming that further work is required before the junction can return to normal.
According to TfL, additional issues have been identified with the water main beneath the roundabout, following recent testing by Essex and Suffolk Water. The discovery means the site is still not ready to fully reopen, extending disruption for local residents and businesses.
While TfL has completed its own major elements of the project—including work on the flyover—efforts are now focused on resolving the remaining utility challenges. Officials say they are considering whether parts of the junction could reopen in stages, but no timeline has yet been confirmed.
The scheme, which involves both the refurbishment of the flyover and the replacement of a key water main, has already faced multiple delays. Initially scheduled for completion in September, the project was later pushed back to spring 2026 after unexpected ground conditions complicated construction work.
Earlier this year, TfL indicated that the roundabout and flyover could reopen by the end of April. However, the latest update suggests that deadline will not be met.
Recent images from the site had shown visible progress, including resurfaced sections of the flyover and newly painted road markings. However, further excavation linked to the water infrastructure has since taken place, underlining the complexity of the ongoing works.
In a statement, TfL’s Director of Capital Delivery, Scott Haxton, acknowledged the frustration caused by the delay. He explained that while progress has been made, additional work is necessary to ensure the water main is fully secure and reliable.
He added that TfL and Essex and Suffolk Water are working closely to complete the outstanding work as quickly as possible and will provide an updated reopening date when it becomes clear.
TfL also apologised to those affected, recognising the continued impact on the surrounding community and businesses as the project runs beyond its expected timeline.