ORR: National Highways must lock in the good progress of the last decade to deliver next Road Period
top of page

ORR: National Highways must lock in the good progress of the last decade to deliver next Road Period

  • Writer: Safer Highways
    Safer Highways
  • Jul 20
  • 2 min read
ree

The Office of Rail and Road (ORR) says that National Highways has delivered significant improvements for road users in the second road period (RP2 2020-2025), but the agency must ‘learn lessons from missed commitments’ in order to deliver better performance in the next Road Period.


According to ORR’s assessment of National Highways’ performance and delivery, published today, over the last five years the company opened 30 major enhancement schemes for traffic with another 11 under construction, achieved improved environmental outcomes, and met targets for clearing incidents; mitigating the impact of roadworks; and maintaining the road surface.

National Highways also made £2.2 billion in efficiency savings, more than its target. This is notable in the context of high inflation during the period, and a significantly altered programme, including the National Emergency Area Retrofit scheme on all lane running smart motorways.

However, National Highways missed, or is likely to miss, five of its 12 key performance indicators, for reasons both within and outside its control.


The five are:

• The number of people killed or seriously injured on the strategic road network;

• Timeliness and accuracy of roadworks information;

• Corporate carbon reduction;

• Mitigation of delay; and

• Road user satisfaction levels.


The agency also did not deliver 11 enhancements to the dates it committed, as well as two of its five renewals outputs commitments, for reasons within its control.


In light of its missed and forecast missed commitments, ORR expects National Highways to use the current time between RP2 and RP3, as it reaches the end of its first decade, to collate the lessons it has learned into a continuous improvement plan, so it can better prepare to meet its commitments and challenges in RP3 and beyond.


ORR also insists that National Highways must continue the good progress it has made to implement its improvement plan following ORR’s investigation into its performance and capability. This includes improving its ability to understand the impacts of interventions, and how these translate into improved performance and delivery for road users.

John Larkinson, ORR chief executive, said:


“Ten years ago, roads reform changed the way England’s strategic roads are planned, funded and delivered. I’m pleased to say that, overall, National Highways has delivered a much better and more efficient network in a challenging environment, and hence those reforms have delivered for road users and taxpayers. But National Highways has missed some important commitments. Looking ahead, there is a tight fiscal environment and a crucial need for National Highways to be a key driver of economic growth. The company must now learn the lessons of its first decade of responsibility for the strategic road network, so that it can deliver more for road users and taxpayers in the next road period.”

 
 
 