top of page
Writer's pictureSafer Highways

Highways England to accelerate more road schemes under Project Speed



More Highways England roads schemes are likely to follow the A66 Transpennine route’s acceleration as part of the Project Speed initiative.


Highways England project director David Haimes told NCE’s Future of Roads conference last week that the roads operator is looking at speeding up delivery of other projects.


“The Project Speed principles of building roads quicker and faster but also considering health and safety and social capita is very much something we are reviewing on schemes,” he said.


“The A66 was very much a path finder scheme. We had a great opportunity to test some of that thinking there.”


Haimes added that there isn’t a “one size fits all” solution.


“It’s about working out target interventions are for each scheme,” he said. “There will be a lot more talk about this in the next couple of months. But the short answer is yes, we need to move faster and also consider the health, safety and wellbeing of the people on that journey.”



The scheme includes the construction of a new bypass, dualling along existing sections of road and major junction improvements.



The time savings have been made by increasing modular and offsite design and construction practices.


Overall, there has been “a left shift of activity” to speed up work.


“All the similar activities need to be undertaken,” Haimes said. “With site investigation and archaeology work normally the approach is to phase these works but on the A66 it was all undertaken within the preliminary design stage.


“This involves getting access to land through negotiations with landowners to gain the information to feed into the design, so we can design once and produce a robust development consent order (DCO). This also enabled the DCO to be brought forward. “

Enabling works have also been brought forward, with early works beginning in April this year.


Haimes explained: “With enabling works on site, close conversations with our statutory utilities partners have enabled us to gain access to start works earlier and get some risk critical activities – including archaeology and statutory utilities – removed before the main works progress.”


The project's DCO is expected to be submitted in 2021/22. Works are scheduled to begin in 2023/24 with the road to be open in 2028/29.


65 views0 comments

Comments


Recent Blog Posts

NEWS AND UPDATES

bottom of page