East Midlands Railway Cuts Intercity Services as Reliability Problems Hit New Aurora Fleet
- Safer Highways
- 8 hours ago
- 3 min read

Temporary emergency timetable introduced after ongoing issues with new Class 810 trains and ageing Meridian fleet leave operator struggling to deliver dependable long-distance services.
Passengers travelling with East Midlands Railway (EMR) are set to face a reduced Intercity timetable after persistent reliability problems affecting both its new Class 810 Aurora trains and existing Class 222 Meridian fleet forced the operator to scale back services.
The temporary timetable, introduced from 20 July, is designed to improve punctuality and provide a more predictable service while engineers work to resolve technical issues that have disrupted operations across the network in recent months.
The move represents a significant setback for EMR's fleet modernisation programme, which was intended to deliver a smooth transition from the ageing Meridian fleet to Hitachi Rail's new bi-mode Aurora trains.
Fleet Transition Fails to Go to Plan
EMR had originally planned to introduce its fleet of 33 Class 810 Aurora trains gradually alongside the existing Class 222s, allowing both fleets to operate in parallel while passengers experienced minimal disruption.
However, the first Aurora train did not enter passenger service until December 2025, more than three years later than originally planned, significantly compressing the introduction programme.
Although the trains received all necessary regulatory approvals and safety certification, operational reliability has fallen well below expectations during their early months in service.
At the same time, maintenance challenges affecting the older Class 222 fleet have further reduced train availability, leaving EMR increasingly unable to operate its planned timetable.
Reliability Takes Priority
Rather than continuing to run an unreliable full timetable, EMR has chosen to temporarily reduce services in an effort to deliver greater consistency for passengers.
The operator says concentrating available rolling stock on fewer services should help reduce cancellations and improve overall reliability while technical improvements continue.
Despite the disruption, EMR has stressed that the decision is intended as a short-term operational measure while work continues with Hitachi Rail to improve fleet performance.
Passengers Feel the Impact
Will Rogers, Managing Director of East Midlands Railway, acknowledged the disappointment the changes will cause for customers.
He said:
"The performance of the Class 810 fleet has fallen below the levels we and our customers expect, and it is necessary to introduce a temporary reduced timetable while we work with the manufacturer, Hitachi Rail, to improve consistency in service."
He added:
"We recognise that this will be disappointing for customers, and we understand the frustration caused when our Intercity services do not consistently meet the standards they rightly expect, which in turn puts our frontline staff in an unenviable position of trying to deliver excellent customer service amidst ongoing reliability challenges."
Hitachi Continues Testing Programme
Hitachi Rail says it remains focused on supporting the introduction of the Aurora fleet while continuing to work closely with EMR and industry partners.
A spokesperson for the manufacturer said:
"The Class 810 fleet has been in passenger service with East Midlands Railway since December 2025 and more than a third of the fleet has now been delivered.
"Hitachi Rail continues to work closely with all industry partners during the entry-into-service phase of the Class 810 fleet, implementing improvements and supporting the transition from the existing fleet to new Aurora trains."
The company also confirmed additional testing is being carried out at the Long Marston Rail Innovation Centre to improve reliability before further trains enter passenger service.
Controlled Rollout to Continue
Despite the operational difficulties, EMR has confirmed it is not suspending the Aurora programme altogether.
Instead, further trains will continue entering service in a carefully controlled manner throughout 2026 and into 2027, with strict reliability targets needing to be achieved before additional units are allocated to full operational diagrams.
At the same time, engineers will continue tackling outstanding maintenance issues affecting the Meridian fleet, with both programmes running in parallel.
A Reminder of the Challenges of Fleet Modernisation
The difficulties experienced by EMR highlight the complexity of introducing new railway fleets while maintaining existing services.
Modern trains bring significant benefits in passenger comfort, accessibility and environmental performance, but the transition period can place considerable pressure on operators as new technology beds in and ageing fleets remain in service longer than originally intended.
For passengers, however, those longer-term benefits offer little comfort today.
With a reduced timetable now in place, EMR's immediate priority is restoring confidence in its Intercity services and delivering the reliable railway customers expect while the Aurora fleet matures into full operational service.